UAB Blount Hall

PROJECT DESCRIPTION

Infrastructure improvements to bring chilled water and steam service from central system into this building at University of Alabama at Birmingham.

PROJECT AT A GLANCE

Location: Birmingham, Alabama
General Contractor: Adkins and Kimbrough Mechanical, LLC
Completion Date: August 2019
Project Budget: $446,800

SPECIFICATIONS:

Bring underground chilled water & steam service from central system into the building mechanical room

Work includes demolition of six boilers, two air cooled chillers, three pumps and piping

New work includes new underground concrete vault

Two steam/hot heating water shell & tube heat exchangers

Pumped condensate return unit

Steam metering station

New steam, condensate return, heating water and chilled water piping

Electrical and controls.